Basement Walkouts

 

Our method for basement walkouts doesn't require an oversized hole. We dig a hole the exact size of the walkout. Then rebar is spaced 18 inches on center each way to form a mat to reinforce the concrete. Next the wall is poured and then the steps are poured with a drain in the bottom. Then the door is placed in the foundation. In the next step, all of the walls are plastered. Lastly, the rail is installed.